METHOD STATEMENT FOR PILE BREAKING
- Mark the correct cutting level using survey instrument and cut along the marking with cutting dish at least 4 centimeter into the core.
FIGURE 1. The pile is cut around it's perimeter by dish grinder with a cutting blade.
(Photo taken from Jizan University Project, Jizan, Kingdom of Saudi Arabia)
Remarks:
Notice that the blinding was casted first before cutting the piles. This method is not advisable because the surface of blinding gets damaged during pile breaking. After breaking the piles, the damaged surface of the blinding has to be rectified before placing waterproofing which is a clear case of double work.
2. Break the pile using large jackhammers up to thirty centimeters above the marked level.
FIGURE 2. About 80% of the length of the pile head is cut down using compressor driven jackhammers.
(Photo taken from Al Rayyan Complex Project, Sharjah, United Arab Emirates, October 2008)
Remarks:
An alternative way of pile breaking is to use the Pile Breaker Machine supplied by Piling Contractors. However, some machine can cut the pile reinforcement during the breaking process that leads to additional work of splicing the reinforcement with couplers.
3. Break the remaining thirty to forty centimeters of pile head by small electric jackhammers and flatten it to
the correct level. Chipping of small loose concrete to be done manually by hammer and chisel.
FIGURE 3. Electric powered light jackhammer is used to achieved the proper level and even surface.
(Photo taken from Al Rayyan Complex Project, Sharjah, United Arab Emirates, October 2008)
Remarks:
A heavy jackhammer cannot be used to leveling the final surface because it breaks the pile head in large chunks. Notice from the picture that the surveyor's rod man is checking the level of the inner side. The outer perimeter of the pile is already in the required level which was previously cut by cutting dish.
4. Finally all pile reinforcement shall be cut to the required development length and all reinforcement with
insufficient development length shall be spliced with couplers.
FIGURE 4. All completed pile heads are marked with masking tape and the pile number is written on the masking tape for reporting purpose.
(Photo taken from Al Rayyan Complex Project, Sharjah, United Arab Emirates, October 2008)
Remarks:
The soil surface is leveled and compacted after completion of pile cutting in preparation for blinding. Casting the blinding after completion of pile breaking is the more advisable sequence of work as this avoids damage to the surface of blinding.
Prepared by : Engineer Raul C. Yalung
Civil & Construction Engineer
I WANT MORE INFORMATION ABOUT THE ABOVE
ReplyDeleteThat is good method for construction
ReplyDeleteNice post! It is a concrete cutting, granite breaking and general demolition solution. This non-explosive demolition agent is easy to use, cost effective and a safer option for silently breaking up hard materials like rock or concrete. Non Explosive Cracking Agent
ReplyDeleteThanks for sharing this info.EXPANDO is the ideal alternative to noisy, risky concrete and rock breaking solutions like explosive blasting, jack hammering, concrete saws and stone cutters - particularly on sites with noise restrictions, vibration issues, safety risks, confined spaces or environmental pollution concerns.
ReplyDeleteNon Explosive Demolition Agent
Do you need extra pile head 10cm even it crused and removed remake 10 cm again or poured with cap concrete
ReplyDeleteQui Cutter is a product from Japan for pile head removal. Well known in Singapore and Australia. See below link;
ReplyDeletehttp://www.silentech.com.au/
https://www.youtube.com/watch?v=GXvIGKJftrc
WHAT IS PILE CHIPPING?
ReplyDeleteI think the term 'chipping' is used for the cutting of bulged shoring piles.
DeleteGreat Blog
ReplyDeletehttps://pilecapinc.com/products/pilecoat-systems/
I'm Абрам Александр a businessman who was able to revive his dying lumbering business through the help of a God sent lender known as Benjamin Lee the Loan Consultant of Le_Meridian Funding Service. Am resident at Yekaterinburg Екатеринбург. Well are you trying to start a business, settle your debt, expand your existing one, need money to purchase supplies. Have you been having problem trying to secure a Good Credit Facility, I want you to know that Le_Meridian Funding Service. Is the right place for you to resolve all your financial problem because am a living testimony and i can't just keep this to myself when others are looking for a way to be financially lifted.. I want you all to contact this God sent lender using the details as stated in other to be a partaker of this great opportunity Email: lfdsloans@lemeridianfds.com OR WhatsApp/Text +1-989-394-3740.
ReplyDelete